Status of Six Laning of NH 10 (Delhi border to Rohtak)
Six laning of NH 10 Delhi/Haryana Border to Rohtak and four lane bypass for Bahadurgarh & Rohtak, NHDP Phase III Project, under Implementation
Status: 31st August 2010Length (Km) 63.49Date of Start May 2008Original Completion Date May 2010Estimate Completion Date May 2011Contractor & Nationality KCT - ERA consortium- IndianSupervision Consultant & Nationality ICT Pvt Ltd- Indian
NHAI have removed the page from Web Site (from Jan 2011) showing “Starting Date” and “Planned Completion Date” “Revised Completion Date” & Name of Consultant etc for running projects. This is BAD & not transparent.
Delhi/ Haryana Border to Rohtak, NH 10, (NHDP Phase III Projects under Implementation Status as on 30th June 2011) Revised Target Date Nov 2011 (By SK Malik, skmlk@yahoo.co.in)